Cambridge Health Alliance
Location: Somerville Hospital
General Contractor: Bent Electrical Contractors, Inc.
Amount: $985,000
Description: Installation of a new addressable fire alarm system throughout the four building complex
General Contractor: Ferrazzani Construction
Amount: $122,894
Description: 5th and 6th floor patient room lighting, power and fire alarm renovations.
General Contractor: Ferrazzani Construction
Amount: $19,921
Description: Mammography / Ultrasound Suite
General Contractor: Ferrazzani Construction
Amount: $396,520
Description: New Endoscopy Suite Project
Location: Cambridge Hospital
General Contractor: Walsh Brothers
Amount: $223,235
Description: Mammography / Oncology Suite
General Contractor: G. Greene Construction
Amount: $118,854
Description: Medical/Surgery Suite Renovation
Location: Whidden Hospital
General Contractor: Ferrazzani Construction
Amount: $99,459
Description: Express Care Suite
Location: Revere Clinic
General Contractor: Lake Contracting
Amount: $60,232
Description: Third floor out patient and clinic and office renovation
Harvard University
General Contractor: Bent Electrical Contractors, Inc.
Location: Biological Laboratory
Amount: $1,100,000
Description: Installation of a new addressable fire alarm system
Location: Carpenter Center Dimming System Lecture/B04
Amount: $40,140
Description: Installation of a Lutron Dimming System in the theater
Location: Geology Building
Amount: $60,765
Description: New addressable fire alarm system
General Contractor: Bluestone Energy Service
Location: Biology Lab Facilities
Amount: $301,523
Description: Lighting Retrofit Project replacement of ballasts, lamps, and fixtures and installation of motion sensors
General Contractor: Marc Truant & Associates
Location: 53 Dunster Street
Amount: $122,018
Description: Historical Renovation Project completely new power, lighting, fire alarm, voice/data systems
Location: Dana Palmer House
Amount: $165,456
Description: Historical Renovation Project completely new power, lighting, fire alarm, voice/data systems
General Contractor: O’Connell Construction
Location: Peabody Museum Lieberman Lab
Amount: $27,850
Description: New laboratory lighting, power, fire alarm and special systems
General Contractor: Richard White & Sons
Location: Riverside Student Housing
Amount: $993,365
Description: Construction of ten new buildings for student housing, power, lighting, fire alarm and site work
General Contractor: Shawmut Design & Company
Location: Biology Hunter Lab
Amount: $146,847
Description: New laboratory lighting, power, fire alarm and special systems
Location: Biology Labs Zebrafish Facility
Amount: $548,681
Description: New Zebrafish with special lighting, dimming controls power, lighting and fire alarm work.
Location: Biological Laboratories
Amount: $524,998
Description: Installation of a new Standby Power Distribution System for lab power and lighting throughout the complex.
Location: Biology Wakely Lab
Amount: $20,772
Description: Alterations of labs and offices
Location: Lyman Lab 3rd/4th floor
Amount: $256,615
Description: Renovation of laboratory lighting, power, fire alarm and special systems
Location: Zhang Lab
Amount: $32,600
Description: Renovation and alterations of offices and labs
Location: MCZ Lobos/Hoekstra Lab
Amount: $339,779
Description: Renovation of reptile and holding room, labs and offices
Location: MCZ 5th Floor
Amount: $22,373
Description: Alteration and renovations of labs and offices
Location: KSG Alumni Affairs & Development Center
Amount: $54,955
Description: Installation of new lighting, dimming, power, fire alarm, HVAC and audio/visual systems
Location: Loker Commons
Amount: $356,714
Description: New student pub and stage. Project consist of new lighting, power, fire alarm, HVAC and dimming and audio/visual systems
General Contractors: Wise Construction
Location: Peabody Museum
Amount: $204,743
Description: Renovation of laboratory lighting, power, fire alarm and special systems
Location: Biology Uchida Labs
Amount: $79,260
Description: Renovation of laboratory lighting, power, fire alarm and special systems
Location: Biology Abzhanov Lab
Amount: $87,949
Description: Renovation of student desk area, offices and labs.
CAAS 29-35 Allen Street
Location: Somerville, MA
General Contractor: Pro-Line Contracting Company
Amount: $156,931
Description of Work: Construction of a new pre-school building with new power, lighting, HVAC, voice/data and fire alarm and special systems
Children's Hospital
Location: Boston, MA
General Contractor: G. Greene Construction
Amount: $407,103
Description: Bed Loss Mitigation project, renovation of patient rooms through out the hospital
Emerson College
Location: Boston, MA
General Contractor: Marc Truant & Associates
Amount: $276,026
Description: Barnes and Noble Book Store, EDC, Rehearsal Studio, New Service & Bike Storage Projects
Genzyme
Location: Cambridge, MA
General Contractor: SRO Companies
Amount: $187,193
Description: New offices lighting, power, HVAC and fire alarm system
Lundgren Management Group
Location: Charlestown
General Contractor: Bent Electrical Contractors, Inc.
Amount: $35,150
Description: Shipway Condos Lighting Project installation of new site lighting
Prudential Building
Location: Boston, MA
General Contractor: Diamond Technologies
Amount: $53,151
Description: Parking Garage installation of four inch conduit runs for voice/data wiring
Raytheon
Location: Woburn MA
General Contractor: Cranshaw Constructions
Amount: $1,594,307
Description: New Missile Defense Headquarters Project installation of new offices, conference rooms, data centers, new power, lighting, emergency systems, HVAC, fire alarm, voice/data and security systems.
Sports Authority #174
Location: Somerville, MA
General Contractor: Wolford Retailer Builders, Inc.
Amount: $374,073
Description: Installation of new building, power, lighting, HVAC and fire alarm system
Super Stop & Shop
Location: Somerville, MA
General Contractor: Testa Corp.
Amount: $165,112
Description: Installation of new 2000 amp service to building and all site parking lot lighting
Tufts University
Location: Tab Building Data Center
General Contractor: Bent Electrical Contractors, Inc.
Amount: $244,154
Description: Installation of new standby generator, automatic transfer switches, new power distribution to the main data center for the university
Location: Michael/Pearson Labs
General Contractor: Bent Electrical Contractor, Inc.
Amount: $370,774
Description: Installation of new standby generator, automatic transfer switches, new standby power distribution systems and branch wiring to every lab in the two chemistry buildings
|